josh
4 Posts
I'm still sort of new to Smedge so its possible that I'm missing an option. Currently under the Work history tab I can see the frames that have "completed" and the frames that are "in-process" but it would be nice to also see the frame that are still "in-Que"

Might also be nice if they were color coded.

Thanks!
   
  Mon, 11/Jul/2011 2:01 PM
Robin
1138 Posts
This has always been a different design concept for Smedge, because the job is not divided up ahead of time. The advantage of not dividing up the job ahead of time is that you can change any parameter of the job, including the frame range to render and the packet size, even while the job is actually going.

However, I have recently thought of a way that the history can "guess" about what the future packets will be and show them as "pending", while still being able to refresh based on changes to the frame range and packet size.

I will be trying to get this into a future release, but probably not into the 2011 update 1 release which is just about ready.

Thanks,
-robin
   
Page 1 of 1

.
.
.
.