> Forum Home > Support > How to display Estimated Remaining time as a custom column in job view?

  Thu, 29/Oct/2015 8:37 PM
Michael
26 Posts
I'd really like to display what smedge thinks the Estimated Remaining time field as a custom column. When I right click a column and select Custom Columns->Add New Custom, I'm not sure what command will return the Estimated Remaining info.

I'm not seeing anything about it in the documentation so I'm wondering if it's even possible? It would IMO be really handy to have as an option rather than just a the progress % bar.

thanks
   
  Mon, 02/Nov/2015 5:08 PM
Robin
1138 Posts
Hi

Currently, this information is not available as it is not part of the Job data, but part of the Job History data, which is kept separate. This is an internal technical reason, however, and can easily be worked around, so I will try to get this in for the next release.

Thanks,
-robin
   